Updated: March 26, 2025
School Name | Project Description | Start Date | Completion Date or Anticipated Date for Completion | Percent Complete |
A.V Graham PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
A.V. Graham PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Amherstburg PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Anderdon PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Anderdon PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 50% |
AV Graham PS | Site Grading Upgrades | 7-01-23 | 10-15-23 | 100% |
Begley PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Begley PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 50% |
Belle River DHS | Building Automation Upgrades (BAS) | 3-01-24 | 8-31-25 | 30% |
Belle River District HS | Camera System Upgrade | 6-01-23 | 7-31-24 | 100% |
Belle River PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Belle River PS | Building Automation Upgrades (BAS) | 3-01-24 | 8-31-25 | 30% |
Bellewood PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Bellewood PS | Building Automation Upgrades (BAS) | 3-01-24 | 12-31-24 | 80% |
Bellewood PS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 0% |
Central PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Central PS | Building Automation Upgrades (BAS) | 3-01-24 | 8-31-25 | 30% |
Central PS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 0% |
Central Public School | Fire Alarm Upgrade | 6-01-23 | 12-01-23 | 100% |
Colchester North PS | Site Grading Upgrades | 7-01-23 | 10-15-23 | 100% |
Coronation PS | Roof Restoration | 7-01-24 | 9-15-24 | 100% |
Coronation PS | Building Automation Upgrades (BAS) | 11-14-24 | 2-15-25 | 100% |
David Suzuki PS | Building Automation Upgrades (BAS) | 03-31-25 | 12-31-25 | 0% |
Davis PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Dougall PS | Building Automation Upgrades (BAS) | 3-01-24 | 12-31-24 | 80% |
East Mersea PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Eastview Horizon PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Essex District HS | Camera System Upgrade | 6-01-23 | 7-31-24 | 100% |
Essex District HS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Essex District HS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Essex PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 0% |
Ford City PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Ford City PS | Building Automation Upgrades (BAS) | 3-01-24 | 12-31-24 | 80% |
Forest Glade PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Forest Glade PS | School Renovation Upgrades - Open concept to closed classroom upgrades, office renovations, creation of new FDK classrooms, custodial room upgrades, window replacement, exterior door replacement, roofing upgrades, masonry restoration, HVAC upgrades, electrical upgrades, LED conversions, parking lot and site grading upgrades, New Kiss n Ride | 2-01-25 | 9-01-26 | 5% |
General Brock PS | HVAC System Upgrades | 12-01-23 | 9-30-24 | 100% |
General Brock PS | Building Automation Upgrades (BAS) | 3-01-24 | 12-31-24 | 80% |
General Brock PS | FDK Exterior Upgrades | 7-01-25 | 9-30-25 | 0% |
General Brock PS | Barrier Free Washroom Upgrades / Sensory Room | 7-01-25 | 8-31-25 | 10% |
Glenwood PS | Office renovation, gym floor replacement, fire alarm upgrades, window replacement, masonry restoration, HVAC system upgrade | 6-01-23 | 12-31-24 | 100% |
Glenwood PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Gore Hill PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Gore Hill PS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 0% |
Gosfield North PS | Kiss n Ride Extension | 5-01-24 | 7-15-24 | 100% |
Gosfield North PS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 0% |
Gosfield North PS | Walking Trail | 7-01-25 | 8-31-25 | 0% |
Harrow PS | School Upgrades - interior finish upgrades, washroom upgrades, office renovation, custodial room upgrades, infill of open concept classrooms, HVAC system upgrade, electrical system upgrade | 7-01-26 | 8-31-27 | 0% |
Hetherington PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Hetherington PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Hugh Beaton PS | Window replacement, exterior door replacement, masonry restoration, HVAC upgrades, electrical upgrades, office renovations, washroom upgrades, sprinkler system upgrades | 7-01-23 | 2-01-25 | 98% |
Hugh Beaton PS | Parking lot upgrades, site grading, FDK play space upgrades | 7-01-25 | 8-31-25 | 0% |
James L Dunn PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
James L Dunn PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
John Campbell PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 0% |
John Campbell PS | Heritage restoration | 7-01-25 | 8-31-25 | 0% |
Kennedy Collegiate | Camera System Upgrade | 9-01-24 | 1-30-25 | 100% |
Kennedy Collegiate | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Kennedy Collegiate | Roof Replacement | 1-30-25 | 3-31-25 | 100% |
Kennedy Collegiate | Program Upgrades (Science Labs, Family Studies, Various Offices, Computer Labs), custodial room upgrades, new staff washrooms, window replacement, exterior doors replacement, roofing restoration and replacement, masonry restoration, HVAC upgrades, electrical upgrades, dust collector replacement | 6-01-23 | 2-01-25 | 98% |
King Edward PS | Building Automation Upgrades (BAS) | 3-01-24 | 12-31-24 | 80% |
King Edward Public School | Public Address System Upgrade | 6-01-23 | 12-01-23 | 100% |
Lakeshore Discovery PS | Roof Restoration | 7-01-24 | 9-15-24 | 100% |
Lakeshore Discovery PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Lakeshore Discovery PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 0% |
Lasalle PS | FDK Upgrades / Paving / Walking Track Upgrades | 7-01-24 | 10-31-24 | 100% |
LaSalle PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
LaSalle PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 0% |
Leamington DHS | Camera System Upgrade | 6-01-23 | 7-31-24 | 100% |
Leamington DHS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Legacy Oak Trail PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Malden Central PS | HVAC System Upgrade | 6-01-24 | 11-30-24 | 100% |
Malden Central PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Malden Central PS | Building Automation Upgrades (BAS) | 3-01-24 | 8-31-25 | 90% |
Margaret D. Bennie PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Marlborough PS | Building Automation Upgrades (BAS) | 03-31-25 | 12-31-25 | 0% |
Marlborough PS | HVAC System Upgrade | 7-01-26 | 8-31-27 | 0% |
Mason Educational Centre | Camera System Upgrade | 6-01-23 | 7-31-24 | 100% |
Mason Educational Centre | Building Automation Upgrades (BAS) | 11-14-24 | 1-31-25 | 100% |
Maxwell PS | Building Automation Upgrades (BAS) | 03-31-25 | 12-31-25 | 0% |
Maxwell PS | HVAC System Upgrade | 7-01-26 | 8-31-27 | 0% |
McWilliam PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
McWilliam PS | Building Automation Upgrades (BAS) | 3-01-24 | 12-31-24 | 80% |
McWilliam PS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 0% |
MD Bennie PS | HVAC System Upgrade | 6-01-24 | 11-30-24 | 100% |
MD Bennie PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
MD Bennie PS | FDK Upgrades / Washroom Upgrades / Energy efficiency upgrades (Windows, Doors, Masonry Repointing) | 03-15-25 | 08-31-26 | 0% |
Mount Carmel PS | Building Automation Upgrades (BAS) | 11-14-24 | 1-31-25 | 100% |
North Star HS | Camera System Upgrade | 9-01-24 | 1-30-25 | 100% |
North Star HS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Northwood PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Northwood PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Northwood PS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 0% |
Northwood Public School | Boiler Replacement | 3-01-23 | 9-30-23 | 100% |
Prince Edward PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Prince Edward PS | Building Automation Upgrades (BAS) | 03-31-25 | 12-31-25 | 0% |
Prince Edward PS | HVAC System Upgrade | 7-01-26 | 8-31-27 | 0% |
Princess Elizabeth PS | HVAC System Upgrade | 6-01-24 | 11-30-24 | 100% |
Princess Elizabeth PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Princess Elizabeth PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Queen Elizabeth PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Queen Elizabeth PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Queen Elizabeth PS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 0% |
Queen Victoria PS | Building Automation Upgrades (BAS) | 03-31-25 | 12-31-25 | 0% |
Queen Victoria PS | HVAC System Upgrade | 7-01-26 | 8-31-27 | 0% |
Riverside SS | Camera System Upgrade | 9-01-24 | 1-30-25 | 100% |
Riverside SS | Special Education Renovations | 4-27-23 | 3-31-24 | 100% |
Riverside SS | Dust Collector Upgrades | 6-01-24 | 11-30-24 | 100% |
Riverside SS | HVAC System Upgrade | 6-01-24 | 8-15-24 | 100% |
Riverside SS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Roseland PS | HVAC System Upgrade | 6-01-24 | 11-30-24 | 100% |
Roseland PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Roseland PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 50% |
Roseville PS | HVAC System Upgrade | 6-01-23 | 10-15-23 | 100% |
Roseville PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Sandwich SS | Track Upgrades | 5-01-23 | 8-15-23 | 100% |
Sandwich SS | Roof Replacement | 7-01-24 | 9-15-24 | 100% |
Sandwich SS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
Sandwich West PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Sandwich West PS | Kiss N Ride Upgrades, FDK play space upgrades | 7-01-25 | 8-31-25 | 0% |
Southwood PS | Site Grading / Walking Path / FDK Upgrades | 7-01-24 | 10-31-24 | 100% |
Southwood PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Southwood PS | Building Automation Upgrades (BAS) | 3-01-24 | 8-31-25 | 30% |
Suzuki PS | Barrier Free Washroom Upgrades | 7-01-25 | 8-31-25 | 10% |
Talbot Trail PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Talbot Trail PS | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 0% |
Tecumseh Vista Academy (E&S) | Camera System Upgrade | 6-01-23 | 7-31-24 | 100% |
Tecumseh Vista Academy (E&S) | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
Tecumseh Vista Academy (E&S) | Building Automation Upgrades (BAS) | 11-14-24 | 8-31-25 | 0% |
Vincent Massey SS | Massey - Curtain Wall / Exterior Doors / Barrier Free / Structural Repairs / Dust Collector / HVAC Upgrades), Barrier Free Assessment | 6-01-24 | 12-31-24 | 98% |
Vincent Massey SS | HVAC System Upgrade | 3-01-25 | 12-15-25 | 5% |
W.F. Herman Academy (E&S) | Camera System Upgrade | 9-01-24 | 1-30-25 | 100% |
W.F. Herman Academy (E&S) | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
W.F. Herman Academy (E&S) | Building Automation Upgrades (BAS) | 3-01-24 | 8-31-25 | 30% |
Walkerville Collegiate | Building Automation Upgrades (BAS) | 3-01-24 | 8-31-25 | 70% |
Walkerville Collegiate | Camera System Upgrade | 9-01-24 | 1-30-25 | 100% |
West Gate PS | Swipe Card Security Access Front End Upgrade | 7-01-24 | 8-31-24 | 100% |
West Gate PS | Building Automation Upgrades (BAS) | 9-01-23 | 7-31-24 | 100% |
West Gate Public School | Camera System Upgrade | 6-01-23 | 7-31-24 | 100% |
Westview Freedom Academy | Site Grading Upgrades | 7-01-23 | 10-15-23 | 100% |
Westview Freedom Academy | Building Automation Upgrades (BAS) | 11-14-24 | 03-15-25 | 100% |